Mt Whaleback Mine – Abrasiguard Slurry Pipe for Tailings Dam Project
BHP’s Mt Whaleback mine is the largest and oldest open cut iron ore mine in the world. It has a production capacity of 43 million tonnes per year.
In 2017, we worked with BHP’s project team to supply the pipework and pipeline assemblies for the mine’s tailings dam wall raise project.
Our Brisbane workshop manufactured 760m of DN300 Abrasiguard slurry piping. A further 2km of slotted polyethylene pipe and Slurryflex mining hose were also custom manufactured for the project. As part of the complete package we supplied spigot assemblies, air valves and support frames, connections and fittings.
We delivered the pipeline to site ready for installation so BHP could successfully commission the pipeline on time and budget.
Client
Year 2017
Project size $1.1M
Location WA
Pipeline length 3km

Related projects

Minjar Pajingo Gold Mine – Slurryflex Hoses for New Tailings Facility

Ngungaju Plant at Pilgangoora – Complete Tailings Dropper System

We're here to help
Got questions? Need advice? Tap into our experience and get specialist advice from our friendly team.


Slurry piping audits
Solve slurry piping maintenance problems for good. No more leaking pipes, no more unplanned shutdowns.