Kalium Lakes Beyondie Project – 1,200 Manual and Actuated Valves
We love being part of new and innovative projects. In 2021, we began working with DRA Global and G&S Engineering Services on the Kalium Lakes Beyondie Project.
It’s an exciting time to be involved the Australian Sulfate of Potash (SOP) industry, with several companies racing to be the first SOP producer in WA.
DRA Global awarded us the valve package for the processing plant, which included 1,200 manual and actuated valves. The valves were assembled, tested and tagged by fitters in our Perth workshop, and delivered to the Beyondie site on time ready for install.
We have continued to provide ongoing support to DRA through installation and commissioning phases.
The first production of SOP is on track for late September 2021.
Client
Year 2021
Location WA
Commodity Sulphate of Potash
Valves supplied 1,200

Related projects

How Roy Hill Solved Costly Unplanned Piping Maintenance for Good

WA Lithium Mine get 12x Longer Wear Life in Slurry Control Valves

8x Longer Lifespan for Cyclone Overflow Piping at FMG Solomon Mine
We're here to help
Got questions? Need advice? Tap into our experience and get specialist advice from our friendly team.


Slurry piping audits
Solve slurry piping maintenance problems for good. No more leaking pipes, no more unplanned shutdowns.