Fekola Gold Mine – Custom SPI Package for New Processing Plant
In 2016, Lycopodium engaged us to supply a custom Special Piping Items (SPI) package for B2Gold’s new Fekola gold processing plant. The Fekola mine, located in Mali, is the company’s largest.
Our SPI package included mining hose, Victaulic couplings and fittings, industrial hose assemblies, Straub couplings, orifice plates, and slotted pipe for tailings dam spigot droppers. We assembled, tested, and tagged the package in our Perth workshop and delivered everything to site in time for the project to commence.
B2Gold successfully commissioned the plant three months ahead of schedule and on budget.
Client
B2Gold client logo
Year 2016–2017
Project size $0.9M
Location Mali
Items supplied 1115
Design engineer Lycopodium
![Fekola Gold Mine](https://www.beaverprocess.com.au/wp-content/uploads/2020/12/Fekola-Gold-Mine-banner-image-1200x675.jpg)
Related projects
![](https://www.beaverprocess.com.au/wp-content/uploads/2024/04/Roy-Hill-Cover-3-360x233.jpg)
How Roy Hill Solved Costly Unplanned Piping Maintenance for Good
![FMG Solomon iron ore mine CLX elbow](https://www.beaverprocess.com.au/wp-content/uploads/2020/12/FMG-Solomon-iron-ore-mine-CLX-elbow-Card-image-360x233.jpg)
8x Longer Lifespan for Cyclone Overflow Piping at FMG Solomon Mine
![](https://www.beaverprocess.com.au/wp-content/uploads/2024/04/Photos-from-Alex-360x233.jpg)